Timezone/Daylight saving interaction?

I have a schedule with a start time 08:00 and end time 17:00, slot size 15.

The Workflow-Scheduling screen shows time from 09:00 through 17:45  (with the Time option set to 'All')

Thus it's as though 1 hour has been added to the shedule start & end times.

Another possible clue: when using the AM & PM Time selections, the boundary is 1300, not 1200 as I would expect.

A further clue: if I move the 'viewed day' back and forward, things change. For 6 Oct and 8 Oct, the display is as expected (and with the AM/PM break at 1200).  However, for today (7 Oct - that day on which the DST change occurred) the 'one hour added' problem appears.

If I scan back and forth across 7 Apr 2013 (when we come off DST), then things are OK on each side, but on 7 Apr the shedule shows as 0700 through 16:45 and the AM/PM break is at 1100.  ie we now have a 'one hour subtracted' problem.

OPV version is 1.5.1; I am doing the development work in Australia on a Win7 system with the timezone set to (UTC+10:00) Canberra, Melbourne, Sydney. 

Conclusion: there is a real bug in the schedule display for the daylight saving change day.  However, since this is always a Sunday, the bug will not be visable with practices that do not operate on Sundays.

Regards, Tim

 

Comment viewing options

Select your preferred way to display the comments and click "Save settings" to activate your changes.

Re: Timezone/Daylight saving interaction?

Just installed build 4842 and can confirm Sun 7/10/12 and Sun 7/4/13 schedule errors.

Re: Timezone/Daylight saving interaction?

I've created a JIRA for this here: OVPMS-1251

-Tim (A)